Resolution to grant outline planning permission*

Cambridge City Council

Given May 2008

Planning Appeal Decision The Planning Inspectorate March 2010

Infrastructure start on site

Countryside Properties

Spring 2010

House building start on site

Countryside Properties with house builders

Winter 2010

Anticipated completion

Countryside Properties with house builders

2019